Electrical/Plumbing Inspection

We had another inspection on Tuesday and happy to see lot of things have been done.

1) Plumbing completed, toilets and tape ware installed

2) Electrical done

3) Doors hardware installed

4) Balcony handrail/balustrade installed

Still carpet, driveway, kitchen splash back, brick mortor/chip and paint touch ups need to be done, we might have PCI at the end of next week if weather clears up to lay the driveway.

We engaged outback to do our landscaping along with the driveway so one less headache after moving.

here are the jobs that outback would do for us

1) RH side of the house - concrete 20 meter long and 1.5 meter wide inc drainage

2) Left side of the house - road base, pebbles and the 400x400 step stone inc drainage

3) In the backyard - Pine timber retaining wall 15m wide and 600mm high
- Pine stairs from Alfresco to the ground
- Brick Plantars on right and left side of the stairs Alfresco to grow herbs
- Provide all the plants
- Clothes line
- Turf

4) In the Frontyard - Herron block retaining walls on the RH and LH of the garage from fence gate
- Block stairs
- Letter box
- Extend the driveway to cover the front porch
- Gardden Edgeing
- Turf

Few Pictures














Tuesday 12 February 2013

Inspection

We had inspection this morning to see the progress. Very happy with the wet areas tiling and the painting, our tilers took more than 2 weeks for the wet areas, was frustrating but paid at the end quality of the work is unbelievable, so impressive. Electricians are coming tomorrow to start the electric fitout .SS gave us roughly 4-5 weeks for the settlement, here are the outstaind items

1) Electrical Fitouts
2) Plumbing to install all the taps etc
3) Kitchen Splashback
4) Driveway
5) All door handles
6) First Floor Carpet














 

Tuesday 5 February 2013

Tiling Continues..

We had chat with tiler today and wet area tiling still continuous., it will take another couple of days to finish. Our tiler is bit slow but we are very happy with the tiling work so far. We have arranged inspection next week Tuesday, will take lot of pictures. Finally painting started today, lets see how long they take to finish it off. We are not too far from PCI , think max 4 weeks?