Saturday 27 October 2012

Gorund Foor Brickwork Completed

On Friday, brickeis have completed the ground floor bricking. Scaffolding is already delivered and will be installed next week and brickies will be back hopefully on Thursday to get the first floor done, so far very happy with the brick work except was a bit of a shock to see the non-coloured side brick showing in the garage but these look perfect neaches to me will do the shelves post handover to hide non-coloured side.






Tuesday 23 October 2012

Framing Finished

Framing has been completed , all the windows, sliding doors and plumbing done. Bricks have been delivered and starting tomorrow. We'll have Independent Frame Inspection before the Gyprock goes in to have piece of mind. Below few pictures



Wednesday 10 October 2012

External Drainage

External Drainage started yesterday and hopefully will be completed today



Wednesday 3 October 2012

Slab Completed


We were expecting to have slab on coming Friday but our SS made our day by informing us slab has poured this morning wow