Sunday 27 January 2013

Garage Door and Front Door

Last week was also productive and lot of items completed

1) Garage door
2) Front door installed
3) All door frames and Skirting completed
4)Wet Area tiling started
5) Range hood installed


 

 

Wednesday 23 January 2013

Lock Up

Finally, we had lock up on Friday, still we are waiting for the front door but for time being they have installed temporary door.



Friday 18 January 2013

Stairs/Kitchen Installed

Amazing two weeks after the break, so much has been done at my site. In these two weeks insulation,gyprock,cornices, Strairs and Kitchen installed. All the doors and skirting/architrave have been delivered. My SS informed me kitchen was supposed to be installed next Wednesday but kitchen company got confused with the dates so they installed this wednesday














Friday 11 January 2013

Insulation & Gyprock

I was not expecting much from EB after holidays but this week has been so productive so far, all credit goes to my SS. Insulation and gyprock done in 3 days and cornices supposed to be installed today, what a week after holidays.

I have advise for everyone, you must visit the site before the gyprock goes in. You should have list of all the gas/water/noggings/power points/tv/foxtel/speaker etc and you spend good time there to tick each and every plumbing/electrical points that is very important, if anything is missed would be hard to get later on esp for the double stories. In my case few things were missing, water conection/noggings/tv points.

Colorbond roof gives different shade at different times of the day but I was able to capture true dune color of the house.



Ceiling/Wall/Sound Screen:





Gyprock:

Media:





Alfresco:



Dinning:


Kitchen:


Family:


Games Area First Floor:


Main Bedroom: